Monday, October 11, 2010

The roof is poured

The Morning began early at 2:45 the concrete mixing crew arrived to start mixing the concrete to pour. All 80 yards of it. yes that is 2:45 in the am. The day went well with only minor problems of running out of water and a belt breaking on one of the 3 mixers. After 6 and 1/2 hours the floor was poured. the pictures show a roof on top of the orphanage that 3 weeks ago was nothing. Glory be to God for sending great men and women to help us get so far. This week we continue the work of the orphanage to keep us on pace to have the framing electrical and plumbing crew arrive on Sunday.

1 comment:

Anonymous said...

It still amazes me that a concrete roof works in earthquake country! Glad you are making progress. God is good! Sue Y (Not really anonymous)